DISTRICT 27

CUMBERLAND COUNTY SR-28 (US-127) bridge construction and paving from north of I-40 (LM 17.8) to near Potato Farm Road (LM 22.7): Construction signs and erosion control measures have been installed. The contractor continues grading activities which will include embankment fill and the placement of graded solid rock. Temporary lane closures and/or periodic traffic stoppages will be necessary as construction activities continue. Utility relocations for gas, water, sewer, and electric are in progress. Motorists should use caution while traveling through the work zone and be aware of reduced speed zones.

[Jones Bros. Contractors, LLC/Bradley/CNV009]

CUMBERLAND COUNTY SR-298 (GENESIS RD.) Utility Work both directions from LM 2.42 to LM 5.92: Shoulder, single lane closures, and rolling roadblock between Cook Road and Wild Azalea Trail. Motorists should reduce their speed and be prepared to stop. Trucks, signage, cones, and flaggers will be present, 12/02/21 through 12/22/21 from 9:00 am – 2:00 pm. [2021-553]

CUMBERLAND COUNTY SR-462 from SR-28 (US-127N / LM 3.1) to SR-298 (Genesis Road / LM 4.6) in Crossville: Construction signs and erosion control measures are installed. Utility relocation activities for gas and sewer are in progress. Construction activities may require temporary lane closures and/or traffic stoppages. Work for the adjoining project will require daytime lane closures of the southbound slow lane on Genesis Road. Motorists should use caution while traveling through the work zone and be aware of reduced speed zones on Interstate Drive.

[Rogers Group, Inc./Bradley/CNV010]

DEKALB COUNTY SR-26 (US-70) grading, drainage, and construction of retaining walls and paving from near SR-53 (LM 2) to near SR-96 (LM 6.1): The contractor has begun grading operations, installing erosion control measures, and water, gas, and electric line relocation. Intermittent lane closures and flagging operations are expected. Intermittent blasting operation has begun resulting in temporary road closures. Motorists are advised to use caution and be alert to all construction signage while traveling through the work zone.

[Twin K Construction/James/CNV012]

DEKALB AND WARREN COUNTY SR-56 construction of bridges and paving from south of Warren-Dekalb county line (LM 24.5) to East Bryant St. (LM 2.9): The contractor will continue installing concrete box culverts and drainage structures. Grade work, bridge work, paving operations, and utility work on the new roadway alignment are ongoing. Traffic has been shifted onto the detour between SR-288 and Old Blue Springs Road for the contractor to complete grade work in the area. Flaggers may be present to move equipment across roadway, unload equipment, or complete utility work. Traffic shifts in Smithville will remain from South College Street to the end of project to allow contractor to complete work. There is a temporary diversion for Ferrell Rd, and one remains in place for Williams Road to allow contractor to construct new alignment. The contractor will be installing a cross drain across SR-56 at the intersection of East Bryant Street on 12/20/21 and 12/21/21. Motorists should use caution in this area while flaggers are present to direct traffic. The speed limit has been reduced to 45 mph in the construction zone. Motorists should use caution in this area and watch for flaggers and construction equipment.

[Jones Bros. Contractors, LLC/Harris/CNT011]

<…….